Time & Work MCQs with Answers | PPSC FPSC CSS NTS — 62 Solved

Time & Work MCQs with Answers – Solved from Past Papers

62 solved Time & Work MCQs collected from real PPSC, FPSC, SPSC, KPPSC, BPSC & NTS past papers (2011–2026). Tap an option to attempt — see correct answer instantly. Download the full PDF for offline revision.

Time & Work Quiz
Score: 0 / 62
Question 1 of 62Not answered

If5 men complete the work 6 days, then in how many days 6 men can complete the same work?

Show solution

Man-days = 5×6 = 30. With 6 men: 30÷6 = 5 days.

Question 2 of 62Not answered

40 men complete one-third of a work in 40 days. How many more men should be employed to finish the rest of the work in 50 more days?

Show solution

1/3 work in 40×40=1600 mandays → full=4800. Remaining 2/3=3200 mandays in 50 days needs 64 men. Additional = 64-40 = 24.

Question 3 of 62Not answered

AandB finish a job in 12 days. While A, B, and C together can finish it in 8 days. How many days will it take for C alone to finish the job?

Show solution

1/C = 1/8 – 1/12 = 3/24 – 2/24 = 1/24. So C alone = 24 days.

Question 4 of 62Not answered

Four men working together can dig a ditch in 42 days. They begin, but one man works only half-days. How long will it take to complete the job?

Show solution

Effective workers = 3.5 (one at half rate). Time = 42×4 ÷ 3.5 = 48 days.

Question 5 of 62Not answered

|facertain job can be finished by 18 workers in 26 days. How many workers are needed to finish job in 12 days?

Show solution

Workers needed = 18×26 ÷ 12 = 39.

Question 6 of 62Not answered

Acandoa piece of work in 4 days and B can do it in 12 days. In how many days will they finish the work, both working together?

Show solution

Together = 4×12 ÷ (4+12) = 48÷16 = 3 days.

Question 7 of 62Not answered

If 8menor 12 women can do a piece of work in 25 days, in how many days can the same work be done by 6 men and 11 women?

Show solution

8M=12W ⇒ 1M=1.5W. So 6M+11W = 9W+11W = 20W. 12W take 25 days → 20W take 12×25/20 = 15 days.

Question 8 of 62Not answered

If 10mencan construct a building in 40 days. How long will it take 1 man to do this work?

Show solution

Mandays = 10×40 = 400. So 1 man takes 400 days.

Question 9 of 62Not answered

Acando work in 6 days and B can do the same work in 12 days. How long will it take if A and B work together?

Show solution

Together = 6×12 ÷ (6+12) = 72÷18 = 4 days.

Question 10 of 62Not answered

If6men take 9 days to complete a work, how many men can complete the work in 3 days?

Show solution

Mandays = 6×9 = 54. In 3 days: 54÷3 = 18 men.

Question 11 of 62Not answered

If 10 workers can make 10 tables in 10 days, then how many days would it take for 5 workers to make 5 tables?

Show solution

1 worker makes 1 table in 10 days. So 5 workers make 5 tables in 10 days.

Question 12 of 62Not answered

6 persons complete a work in 16 days, 8 persons will complete the job in how many days?

Show solution

Mandays = 6×16 = 96. With 8: 96÷8 = 12 days.

Question 13 of 62Not answered

\fAand B together can complete a piece of work in 15 days and B alone in 20 days, in how many days can A alone complete the work?

Show solution

1/A = 1/15 – 1/20 = 4/60 – 3/60 = 1/60. So A alone = 60 days.

Question 14 of 62Not answered

Aworker did work 1 week and 3 days for Rs. 750. In one month how much he got money?

Show solution

Per day wage = 750÷10 = 75. In 30 days = 75×30 = 2250 Rs.

Question 15 of 62Not answered

Ali earns Rs 7500 in 2 weeks what will he earn in 2 days if he works 6 days a week?

Show solution

Per day = 7500÷12 = 625. In 2 days = 1250 Rs.

Question 16 of 62Not answered

Ais 4times as fast as B and therefore is able to finish the work in 45 days less than B. A and B, can complete the work in how many days?

Show solution

Let B=x, A=x/4. x – x/4 = 45 → 3x/4=45 → x=60, A=15. Together = 60×15 ÷ 75 = 12 days.

Question 17 of 62Not answered

AandB together can complete a work in 3 days. They start together but, after 2 days, B left the work. If the work is completed after 2 more days, B alone could do the work in?

Show solution

In 2 days together, 2/3 work done. Remaining 1/3 done by B alone in 2 days → B = 6 days.

Question 18 of 62Not answered

A project of construction of a building can be completed by 150 workers in 40 days. But project manager brought 30 more workers after 16 days. In how many days will the remaining work be finished?

Show solution

Total = 150×40 = 6000 mandays. After 16 days, 2400 done, 3600 left. With 180 workers: 3600÷180 = 20 days.

Question 19 of 62Not answered

lf 10 persons can do a work in 20 days than 20 persons with twice efficiency can do the same work in?

Show solution

10 persons × 20 days = 200 mandays. 20 persons with 2× efficiency = 40 equivalent → 200÷40 = 5 days.

Question 20 of 62Not answered

AandBcan doa piece of work in 12 days B and Cin 15 days A and Cin 20 days than the number of days taken by A Band C together to finish the work are?

Show solution

1/(A+B)+1/(B+C)+1/(A+C) = 1/12+1/15+1/20 = 12/60 = 1/5. So 2(rate_total)=1/5 → all together = 10 days.

Question 21 of 62Not answered

Working 5 hours a day, A can Complete a work in 8 days and working 6 hours a day, B can complete the same work in 10 days. Working 8 hours a day, they can jointly complete the work in?

Show solution

A=8×5=40 hrs, B=10×6=60 hrs. Combined rate = 1/40+1/60 = 1/24. Total = 24 hrs ÷ 8 hrs/day = 3 days.

Question 22 of 62Not answered

60 men can doa work in 40 days. How long will it take 40 men to complete the same work?

Show solution

Mandays = 60×40 = 2400. With 40 men: 2400÷40 = 60 days.

Question 23 of 62Not answered

42 women can do a piece a work in 18 days. How many women be required to PREPARATION WI do the same piece of work in 21 days?

Show solution

Women needed = 42×18 ÷ 21 = 36.

Question 24 of 62Not answered

Xand Y can doa piece of work in 20 days and 12 days respectively. X started the work alone and then after 4 days Y joined him till the completion of the work. How long did the work last?

Show solution

X alone 4 days = 4/20 = 1/5 done. Left = 4/5. Together rate = 1/20+1/12 = 2/15. Time for rest = 6 days. Total = 4+6 = 10 days.

Question 25 of 62Not answered

Ais twice as good as B as a workman. A takes 30 days less than B. How many days does both complete the work?

Show solution

Let B=x, A=x/2. x – x/2 = 30 → x=60, A=30. Together = 60×30 ÷ 90 = 20 days.

Question 26 of 62Not answered

36men can complete a piece of work in 18 days. In how many days will 27 men complete the same work?

Show solution

Days = 36×18 ÷ 27 = 24.

Question 27 of 62Not answered

If 10mencan doa piece of work in 12 days, the time taken by 12 men to do the same piece of work will be?

Show solution

Days = 10×12 ÷ 12 = 10.

Question 28 of 62Not answered

Ais twice as good as workman as B and together they finish a piece of work in 18 days. In how many days will B alone finish the work?

Show solution

A's rate = 2× B's. Combined 3r = 1/18 → r = 1/54. So B alone = 54 days.

Question 29 of 62Not answered

If 1 day work = 1/20 then time required to finish the job (in days)?

Show solution

If 1 day = 1/20 of work, then full work = 20 days.

Question 30 of 62Not answered

AandB together can complete a piece of work in 4 days. If A alone can PREPARATION WI1 complete the same work in 12 days, in how many days can B alone complete that work?

Show solution

1/B = 1/4 – 1/12 = 3/12 – 1/12 = 2/12 = 1/6. So B = 6 days.

Question 31 of 62Not answered

56 men can do apiece of work in 24 days. In how many days can 42 men complete the same piece of work?

Show solution

Days = 56×24 ÷ 42 = 32.

Question 32 of 62Not answered

3 pumps, working 8 hours a day, can empty a tank in 2 days. How many hours a day must 4 pumps work to empty the tank in 1 day?

Show solution

Pump-hours = 3×8×2 = 48. For 4 pumps × 1 day: 48 ÷ 4 = 12 hours/day.

Question 33 of 62Not answered

39 persons can repair a road in 12 days, working 5 hours a day. In how many days will 30 persons, working 6 hours a day, complete the work?

Show solution

Total work = 39×12×5 = 2340 person-hours. With 30 persons × 6 hrs/day: 2340 ÷ 180 = 13 days.

Question 34 of 62Not answered

71.A man anda boy received Rs. 800 as wages for 5 days for the work they did together. The man’s efficiency in the work was three times that of the boy. What are the daily wages of the boy?

Show solution

Man's rate = 3× boy's. Per day = 800÷5 = 160. Then 3b+b=160 → b = 40 Rs/day.

Question 35 of 62Not answered

{If 24 men can finish a work in 10 days, then find the number of days required to complete the same work by 30 men?

Show solution

Days = 24×10 ÷ 30 = 8.

Question 36 of 62Not answered

Aninlet pipe can fill a tank in 10 hours and an outlet pipe empties the same full tank in 20 hrs. The time required to PREPARATION WI1 fill the tank when both pipes are opened?

Show solution

Net rate = 1/10 – 1/20 = 1/20. So tank fills in 20 hours.

Question 37 of 62Not answered

|f10mencan construct a building in 40 days, how long will it take 20 men to do this work?

Show solution

Days = 10×40 ÷ 20 = 20.

Question 38 of 62Not answered

If 16 machines do a piece of work in 4 days, then 8 machines will do the same job in days?

Show solution

Days = 16×4 ÷ 8 = 8.

Question 39 of 62Not answered

If 20 mencan doa piece of work in 8 days, how many men will finish it in 10 days?

Show solution

Men = 20×8 ÷ 10 = 16.

Question 40 of 62Not answered

Pipe “A” can fill a tank in 5 minutes whereas “B” can fill it in 6 minutes. How long would it take both pipes, working together, to fill it?

Show solution

Together = 5×6 ÷ (5+6) = 30/11 minutes.

Question 41 of 62Not answered

If 16 men complete work in 10 days how much days are required completing work by 8 men?

Show solution

Days = 16×10 ÷ 8 = 20.

Question 42 of 62Not answered

If 8 people work for 60 days how many days will it take for 6 people to complete the same work?

Show solution

Days = 8×60 ÷ 6 = 80.

Question 43 of 62Not answered

10 men, working 6 hours a day can complete a work in 18 days. How many hours a day must 15 men work to complete the work in 12 days?

Show solution

Total work = 10×6×18 = 1080 man-hours. With 15 men × 12 days: 1080 ÷ 180 = 6 hours/day.

Question 44 of 62Not answered

A person can doa work in 10 days but another can do it in 15 days. In how many days, they will complete the task if work together?

Show solution

Together = 10×15 ÷ 25 = 6 days.

Question 45 of 62Not answered

If 10 men can doa piece of work in 20 days, how long will it take 8 men to do the same job if they work at the same rate?

Show solution

Days = 10×20 ÷ 8 = 25.

Question 46 of 62Not answered

7mencan complete a piece of work in 12 days. How many additional men will be required to complete double the work in 8 days?

Show solution

Mandays for double work = 2×7×12 = 168. In 8 days needs 168÷8 = 21 men. Additional = 21-7 = 14.

Question 47 of 62Not answered

If 15 men can doa piece of work in 20 days then in how many days can 25 men finish the same work?

Show solution

Days = 15×20 ÷ 25 = 12.

Question 48 of 62Not answered

40 men can do work in 50 days. How long it will take 25 men to do the work?

Show solution

Days = 40×50 ÷ 25 = 80.

Question 49 of 62Not answered

Iften men can doa piece of work in twenty days, how long will it take if 8 men do the job when they work at the same rate?

Show solution

Days = 10×20 ÷ 8 = 25.

Question 50 of 62Not answered

Amir does a work in 10 days and Babar does the same work in 15 days. In how many days do they together complete the same work?

Show solution

Together = 10×15 ÷ 25 = 6 days.

Question 51 of 62Not answered

16 men build a house in 10 days. How much time will it take 8 men to do this work?

Show solution

Days = 16×10 ÷ 8 = 20.

Question 52 of 62Not answered

5 workers, working 8 hours a day, finished painting a house in 2 days. If an identical house has to be painted completely in a day by 8 workers, how many hours should they work?

Show solution

Worker-hours = 5×8×2 = 80. With 8 workers × 1 day: 80÷8 = 10 hours.

Question 53 of 62Not answered

If 15 men complete a work in 20 days, then 25 men will complete that work in how much days?

Show solution

Days = 15×20 ÷ 25 = 12.

Question 54 of 62Not answered

12 men build a house in 24 days. How much time will it take 8 men to do this work?

Show solution

Days = 12×24 ÷ 8 = 36.

Question 55 of 62Not answered

|f15 mencan doa piece of work in 8 days, how many men will finish it in 10 days?

Show solution

Men = 15×8 ÷ 10 = 12.

Question 56 of 62Not answered

If 3 menor 6 boys can do a work in 20 days, then 6 men and 8 boys shall do it in?

Show solution

3 men = 6 boys ⇒ 1 man = 2 boys. So 6M+8B = 12B+8B = 20B. 6 boys take 20 days → 20 boys take 6×20÷20 = 6 days.

Question 57 of 62Not answered

If 200 men can do a piece of work in 8 days, how many men will finish it in 10 days?

Show solution

Men = 200×8 ÷ 10 = 160.

Question 58 of 62Not answered

Acandoa piece of work in 10 days and B can do it in 15 days. The number of days required by them to finish it, working together is?

Show solution

Together = 10×15 ÷ 25 = 6 days.

Question 59 of 62Not answered

10mencan complete a job in 14 days. How long will it take 4 men to finish the same job if they work at the same rate?

Show solution

Days = 10×14 ÷ 4 = 35.

Question 60 of 62Not answered

8&mencan doa work in 60 days. How long will it take 6 men to do the work?

Show solution

Days = 8×60 ÷ 6 = 80.

Question 61 of 62Not answered

20mencan construct a building in 40 days. How long will it take 10 men to do this work?

Show solution

Days = 20×40 ÷ 10 = 80.

Question 62 of 62Not answered

120 men are used to build a huge building for 30 days. How long will it take 80 men to do the same work?

Show solution

Days = 120×30 ÷ 80 = 45.

Time & Work MCQs for PPSC, FPSC, NTS & All Pakistani Competitive Exams

Time & Work is one of the most-tested word-problem topics in Pakistani competitive exam Math. From PPSC Lecturer, Sub-Inspector and Tehsildar tests to FPSC CSS Screening (MPT), NTS NAT/GAT, OTS, CTS, KPPSC, SPSC, BPSC and AJKPSC — almost every paper contains 1 to 5 time-and-work questions. Mastering this one topic alone can secure 2–5 marks in any One Paper format exam because every question reduces to the same work-rate logic.

QuizWing has compiled 62 verified time & work MCQs from real past papers spanning 2011–2026 — every question solved from scratch by AI and answer keys verified. The bank covers single-worker rates, combined work (two or three workers), man-day equivalence, pipes & cistern problems, work-in-stages, and wages distribution by work-rate.

What types of time & work questions appear?

  • Basic work-rate — “If A finishes a job in 12 days, what is A’s daily rate?” → 1/12
  • Combined work (A + B) — “A in 10 days, B in 15 days; together?” → 6 days
  • Find third worker — “A+B in 12 days, A+B+C in 8 days; find C alone” → 24 days
  • Man-day problems — “5 men finish in 6 days; how many days for 6 men?” → 5 days
  • Pipes & cistern — filling and emptying pipes working together / opposite
  • Work-in-stages — X works for 4 days then leaves, Y completes the rest
  • Wages distribution — wages split in ratio of work done by each person

Key time & work formulas

If A finishes in `a` days → A’s rate = 1 ÷ a per day
Combined: time together = (a × b) ÷ (a + b)
Three workers: time = abc ÷ (ab + bc + ca)
Man-day equivalence: M₁ × D₁ × H₁ = M₂ × D₂ × H₂ (for same work)
Pipes: net rate = sum of inflow rates − sum of leak rates
Wages ratio = work-rate ratio = inverse ratio of times

Mental-math shortcuts

  • Combined work shortcut — for two workers with a, b days: time = ab ÷ (a + b). Memorise!
  • Inverse-ratio trick — if A is 3× faster than B, A’s time = B’s time ÷ 3
  • Common LCM anchor — pick LCM(a, b) as total work units; each rate becomes a whole number
  • Man-day cross-multiply — M₁D₁ = M₂D₂ for the same job; for partial work use fractions
  • Pipe + leak — if pipe fills in p hours and leak empties in L hours, net time = pL ÷ (L − p)
  • Wages — if A does w₁ work and B does w₂ work, wages split as w₁ : w₂

How to use this page for revision

Quiz mode: Tap any option — green = correct, red = wrong. Use the pagination buttons to move between sets of 25 MCQs at a time.

PDF download: Click Download PDF in the sticky bar to grab all 62 MCQs with answers for offline study.

Mixed practice: attempt our full PPSC Mock Test with all subjects + weighted distribution to simulate the real exam.

Time & Work weightage by exam

ExamTypical Time & Work MCQsMarks Share
PPSC One Paper1–32–5
FPSC Screening2–54–8
NTS NAT / GAT3–65–10
CSS Screening (MPT)3–66–12
OTS / CTS2–43–7
SPSC / KPPSC / BPSC1–32–5

All MCQs sourced from official past papers of PPSC, FPSC, SPSC, KPPSC and NTS. Found a wrong answer? WhatsApp 0302-1417839 — we fix every reported issue within 24 hours.

Frequently Asked Questions

Typically 1 to 3 geometry MCQs appear in every PPSC One Paper test (Sub-Inspector, Tehsildar, Junior Clerk, Lecturer, BPS-14/16/17). FPSC, NTS and CSS papers tend to include 2–5. Mastering this topic alone secures 2–5 guaranteed marks because most questions reduce to the same area, perimeter, angle and volume formulas.

Based on our analysis of 62 past-paper MCQs (2011–2026), the three most-recurring types are: (1) area of triangle / rectangle / circle, (2) polygon interior angle problems, and (3) volume & surface area of cube, cylinder and sphere.

No. Calculators are not allowed in PPSC, FPSC, NTS, OTS or any provincial commission exam. Practise mental math shortcuts — 10%, 25%, 50% calculations should take under 5 seconds.

Yes for PPSC and FPSC — 0.25 marks deducted per wrong answer. Strategy: if you can eliminate 2 out of 4 options confidently, attempt it; otherwise leave blank.

Yes — click the Download PDF button in the sticky bar at the top of the quiz section. You get all 62 MCQs with answers in a branded QuizWing PDF, free, no signup.

Yes — 100% transferable. All provincial public service commissions follow a near-identical Math syllabus. The same geometry MCQs appear (often verbatim) in SPSC, KPPSC, BPSC, AJKPSC and NTS NAT/GAT papers.

Message us on WhatsApp at 0302-1417839 with the question number and what you believe the correct answer should be. We verify against multiple sources and fix every reported issue within 24 hours.

Written by
Sadaqat Ali

Assistant Commissioner and competitive-exam expert. Sadaqat writes and reviews QuizWing's One Paper preparation content across all subjects — General…

More articles by Sadaqat Ali →

Leave a Comment